Glossary of GMP production scheduling

The terms below describe what governs a production schedule in a GMP plant. Where a term has a regulatory basis, the definition names the document it comes from.

Production scheduling (GMP)

Sequencing batches on equipment over time so the plan respects validated constraints and can be executed on the floor. It differs from discrete manufacturing scheduling because several of the constraints have a regulatory basis rather than an operational one.

Constraint model

The set of rules that govern what can run where and in what order, with the document each rule came from attached. Most sites hold this knowledge across validation reports, S&OP material, maintenance systems and individual planners rather than in one reviewable place.

Dirty and clean hold time

The maximum time allowed between manufacture and cleaning, and between cleaning and use. EudraLex Volume 4 Annex 15 section 10.8 requires both to be defined for the cleaning process, so they are established limits rather than durations a planner estimates.

Campaign length

The maximum number of batches or period of time a campaign may run before a validated cleaning procedure. Annex 15 section 10.9 makes it the basis of the cleaning validation exercise, and Health Canada builds the maximum into its definition of campaign production, so extending a campaign changes a control measure rather than saving a changeover.

Changeover

The cleaning and setup between two different products on the same equipment. Health Canada defines a changeover procedure as a logical series of validated steps ensuring proper cleaning of suites and equipment before a different product begins.

Equipment qualification and operator certification

The status that determines which suite can run which product and which person may run it. Both must be renewed periodically, through requalification and retraining, and a published plan becomes unexecutable when either lapses.

Batch release

The decision to approve or reject a batch, taken by the authority each regulator names: the quality control unit under 21 CFR 211.22, the quality control department under Health Canada's GUI-0001, and the Qualified Person in the EU. It is a decision point rather than a fixed lead time, and the answer is not always yes.

Audit trail

A secure, time-stamped record allowing reconstruction of how something was created, modified or deleted. MHRA describes it as capturing the who, what, when and why of an action; a production schedule typically records the first three.

Finite-capacity scheduling

Sequencing against real resource availability rather than assuming infinite capacity. MRP runs in the ERP are often infinite by design, with finite scheduling performed as a separate step.

Single-planner dependency

A site where the constraint logic that governs the schedule exists mainly in one person's judgment. It shows no symptoms until that person leaves.

ISA-95

The international standard for integrating enterprise and control systems, published as IEC 62264. It names plant production scheduling at Level 4 and detailed production scheduling at Level 3, which is why ERP and MES vendors both claim the function.